Route 198 Expressway |
Description: Near Hanford from on Route 198 from 1.3 miles east of Route 43 in Kings County to 0.4 miles west of Route 99 near Visala in Tulare County. Convert to a four-lane expressway. (TCR #111)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Kings, Tulare |
City | |
Zip Code | 93230, 93277, 93291 |
Senate District |
16 |
Assembly District | 30 |
Congressional District | 20, 21 |
Caltrans District |
06 |
County/State Route | Tulare 198 |
Postmile Begin/End | R 0 R 3.3 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 875 | 1,233 |
Lane Miles Added (Mixed) | 20.2 | 20.2 |
Peak Period Time Savings (minutes) | 10453 | 12,607 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Neil Bretz | (559) 243-3465 | neil.bretz@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Neil Bretz | (559) 243-3465 | neil.bretz@dot.ca.gov | |
Right of Way Phase |
Caltrans | Neil Bretz | (559) 243-3465 | neil.bretz@dot.ca.gov | |
Construction Phase |
Caltrans | Neil Bretz | (559) 243-3465 | neil.bretz@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Paul-Albert Marquez | (559) 445-5867 | paul-albert.marquez@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$71,600 | $-27,328 | $44,272 | ||||
Non-bond Funding | |||||||
State/Federal* |
$50,367 | $-3,025 | $47,342 | ||||
Local** |
$2,400 | $260 | $2,660 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $124,367 | $-30,093 | $94,274 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,549 | $490 | $2,039 | $1,982 | |||
Design(PS&E) |
$4,253 | $1,515 | $5,768 | $6,168 | |||
Right of Way |
$13,518 | $11,919 | $25,437 | $27,453 | |||
Construction |
$105,047 | $-44,017 | $61,030 | $60,792 | |||
Total* | $124,367 | $-30,093 | $94,274 | $96,395 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
07/01/1998 06/01/2003 |
|
07/01/1998 06/01/2003 |
100 | 09/02/1997 06/30/2003 |
10 -1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2003 10/01/2008 |
|
06/01/2003 10/01/2008 |
100 | 08/01/2001 10/01/2008 |
22 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
03/01/2006 05/01/2009 |
|
03/01/2006 05/01/2009 |
100 | 12/17/2001 05/08/2009 |
51 0 |
|
Begin Construction Phase
End Construction Phase |
08/01/2009 02/01/2012 |
|
10/01/2009 02/01/2012 |
0 | 09/01/2009 03/11/2013 |
1 -13 |
|
Begin Closeout Phase
End Closeout Phase |
02/01/2012 08/01/2013 |
|
02/01/2012 08/01/2013 |
0 | 03/11/2013 03/17/2016 |
-13 -32 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 10/01/2008 | 10/01/2008 | 0 | 0 | |||
Implementation Date | 04/01/2009 | 04/01/2009 | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 875 | 1,233 |
Lane Miles Added (Mixed) | 20.2 | 20.2 |
Peak Period Time Savings (minutes) | 10453 | 12,607 |
Bond Funding Cost | |
---|---|
Adopted: |
$71,600,000 |
Current Approved: |
$44,514,000 |
Actual Expenditures: |
$44,514,000 |
Status as of December 31, 2023.