Route 198 Expressway

Description: Near Hanford from on Route 198 from 1.3 miles east of Route 43 in Kings County to 0.4 miles west of Route 99 near Visala in Tulare County. Convert to a four-lane expressway. (TCR #111)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kings, Tulare
City
Zip Code 93230, 93277, 93291
 
Senate District
16
Assembly District 30
Congressional District 20, 21
 
Caltrans District
06
 
 
County/State Route Tulare 198
Postmile Begin/End R  0 R  3.3
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  875    1,233  
Lane Miles Added (Mixed)  20.2    20.2  
Peak Period Time Savings (minutes)  10453    12,607  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Neil Bretz (559) 243-3465   neil.bretz@dot.ca.gov
Design (PS&E) Phase
Caltrans Neil Bretz (559) 243-3465   neil.bretz@dot.ca.gov
Right of Way Phase
Caltrans Neil Bretz (559) 243-3465   neil.bretz@dot.ca.gov
Construction Phase
Caltrans Neil Bretz (559) 243-3465   neil.bretz@dot.ca.gov
 
Corridor System Management Plan
Caltrans Paul-Albert Marquez (559) 445-5867   paul-albert.marquez@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$71,600 $-27,328 $44,272
Non-bond Funding
State/Federal*
$50,367 $-3,025 $47,342
Local**
$2,400 $260 $2,660
Non Budgeted ETC
$0 $0 $0
 
Total**** $124,367 $-30,093 $94,274

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,549 $490 $2,039 $1,982
Design(PS&E)
$4,253 $1,515 $5,768 $6,168
Right of Way
$13,518 $11,919 $25,437 $27,453
Construction
$105,047 $-44,017 $61,030 $60,792
 
Total* $124,367 $-30,093 $94,274 $96,395

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/1998 

06/01/2003 
 

 
07/01/1998 

06/01/2003 
100  09/02/1997 

06/30/2003 
10 

-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2003 

10/01/2008 
 

 
06/01/2003 

10/01/2008 
100  08/01/2001 

10/01/2008 
22 

Begin Right of Way Phase

End Right of Way Phase
03/01/2006 

05/01/2009 
 

 
03/01/2006 

05/01/2009 
100  12/17/2001 

05/08/2009 
51 

Begin Construction Phase

End Construction Phase
08/01/2009 

02/01/2012 
 

 
10/01/2009 

02/01/2012 
09/01/2009 

03/11/2013 


-13 
Begin Closeout Phase

End Closeout Phase
02/01/2012 

08/01/2013 
 

 
02/01/2012 

08/01/2013 
03/11/2013 

03/17/2016 
-13 

-32 
Corridor System Management Plan
Adoption Date 10/01/2008    10/01/2008   
Implementation Date 04/01/2009    04/01/2009   
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 875 1,233
Lane Miles Added (Mixed) 20.2 20.2
Peak Period Time Savings (minutes) 10453 12,607

Bond Funding Cost
Adopted:
$71,600,000
Current Approved:
$44,514,000
Actual Expenditures:
$44,514,000

 

Status as of December 31, 2023.